50 Hayes Rd, Newborough.
We’re excited to see Civil Package 1 at Narracan Lakes nearing completion, bringing us one step closer to creating this beautiful lakeside community.
Pavement works have now progressed to Class 2, with the final asphalt layer scheduled for completion on 10 October. Topsoil installation is also 90% complete, with final authority testing and compliance works currently underway.
With these milestones achieved, we look forward to progressing into Civil Packages 2 and 3 and seeing the community continue to take shape.